Sterling Office Buildout
Commercial

Sterling Office Buildout

All Case Studies
Location

Burnaby

Budget

$120K–$160K

Timeline

20 weeks

Status

Completed

Scope Summary

Tenant improvement for a 4,500 sqft office space, including demising walls, a new kitchenette, two private offices, a glass-fronted conference room, polished concrete floors, and full HVAC reconfiguration.

Before & After

Sterling Office Buildout beforeBefore
Sterling Office Buildout afterAfter

Challenge & Solution

The Challenge

The lease required the tenant to take occupancy by a fixed date, but the space was a bare concrete shell with no partitions, no plumbing, and a single HVAC zone. The building manager required all work to be done after business hours to avoid disrupting other tenants.

The Solution

We worked closely with the tenant's designer to finalize the floor plan before demolition began, which let us pre-fabricate the demising wall framing off-site and stage materials in a ground-floor loading bay. By pre-assembling the wall sections, we cut the framing phase from two weeks to four days.

The polished concrete floor was poured and ground in three sections over a weekend to avoid curing time conflicts. The glass-fronted conference room uses a steel channel system that we installed and glazed in a single day. All rough-ins — electrical, data, and plumbing — were coordinated through a single foreman to avoid trade overlap and keep the after-hours schedule on track.

The tenant moved in on schedule, one day ahead of the lease deadline.